Despite the inclement conditions, the construction of 47 lots in Stage 1 is well underway with earthworks and sewer drainage all completed.
Road boxing and stabilisation are at 90% complete and water reticulation, road crossings and road construction layers are all underway.
Construction is forecast to be completed in January 2024, with title & settlements commencing March 2024. Stage 2 construction will commence in November 2023.